Skip to the main content
CONTRACT AWARDUpdated 1 months ago

REHABILITATION OF THE CONTADOR HYDRO POWER PLANT (HPP) IN SÃO TOMÉ É PRÍNCIPE (PENSTOCK, POWER HOUSE, VALVES, AND PROTECTION WALLS)

World Bank-financed contract awarded to GHCB ANGOLA - GUANGXI HYDROELECTRIC CONSTRUCTION BUREAU,S.A. for the Sao Tome and Principe STP Power Sector Recovery Project project (Project ID P157096).

English, French, Portuguese or Arabic, machine translated, with the original kept beside it.
Key Information
Awarded by
Government of Sao Tome and Principe (World Bank-financed, project P157096)
Location
Sao Tome and Principe, Sao Tome and Principe
Status
Awarded
Category
Works
Award Amount
USD 4,448,348
Size
large
Reference
1855781
Procurement Method
Request for Bids
Language
English
Awarded to
GHCB ANGOLA - GUANGXI HYDROELECTRIC CONSTRUCTION BUREAU,S.A.

Overview

Contract awarded under World Bank-financed project P157096 (STP Power Sector Recovery Project). Borrower: Government of Sao Tome and Principe. Procurement category: Works. Method: Request for Bids. Review type: Post. Fiscal year: 2024. Supplier of record (per World Bank STEP): GHCB ANGOLA - GUANGXI HYDROELECTRIC CONSTRUCTION BUREAU,S.A. (Angola). Borrower contract ref: 121/W/PRSE/2023. Source: World Bank Contract Awards in Investment Project Financing dataset, daily updated from STEP.

Selection Criteria

Selected through Request for Bids procurement procedure under World Bank Procurement Regulations. Procurement category: Works. Subject to Post review by the World Bank.