Back to contract awards
CONTRACT AWARD ✓ Verified Updated 5 days ago

Construction of Kankan 225/30 kV Substation, PIEGM

Engineering, supply and construction of the Kankan 225/30 kV substation under the Guinea-Mali Electricity Interconnection Project (PIEGM), financed by IDA credits 62610 and D3360.

Key Information
Awarding Country
Awarded By
Electricite de Guinee (EDG)
Status
In Progress
Contract Value
USD 13,167,065
Procurement Method
Open
Reference
P166042-WORKS-SUBSTATION-KANKAN
View Original Announcement Opens on the original publisher's site

Description

Works contract under the Guinea-Mali Interconnection Project (P166042). Scope covers design, supply and installation of high-voltage equipment including a 225/30 kV transformer, switchgear, control and protection systems, and commissioning of the Kankan substation. Initial contract value USD 9,358,505.21, with a price adjustment of USD 3,808,560.16 representing 40.69 percent of the initial contract. As of 30 September 2024 the overall physical progress was 69.55 percent. The previous implementation mission noted slow progress due to inadequate mobilization of material and human resources by the contractor. Since that mission, the contractor deployed additional staff and machinery on site, allowing the progress rate to reach 69 percent. The main electrical equipment including the transformer was shipped and expected for delivery in Conakry by 30 November 2024. Completion of works is scheduled for 28 February 2025. Contractor name not disclosed in the public Implementation Status Report.

Scope of Work

Design, supply and installation of 225/30 kV transformer and high-voltage switchgear, control and protection systems, civil works, commissioning, and operator training for the Kankan substation.

Why This Supplier Won

Contractor identity not named in the public Implementation Status Report. Initial contract value USD 9,358,505.21 with a subsequent price adjustment of USD 3,808,560.16 (+40.69 percent). Project is financed by IDA credits 62610 and D3360 under the Guinea-Mali Interconnection Project P166042.

Sectors

Energy Power Transmission Substations

Source

World Bank Implementation Status and Results Report (ISR02057), Guinea-Mali Interconnection Project P166042, archived 14 November 2024

Related Contract Awards

Guinea

Trav réhab. de 39,811 km de pistes reliant les sites de RN1 Kouria-Taady Bondokhori, Carref (RN1) Koba-Koba, Wonkifong-Balaya, Carref Balaya-Digue Folon et Carrefour Balaya-RN4 à Coyah (Lot9 DAO)

USD 1,157,304
Guinea

Réhabilitation des locaux de la CRIEF

USD 1,174,284
Guinea

Travaux de réhabilitation de 39,80 km de pistes (route de désenclavement) reliant les sites de Kolia Sanamato-Thiéckèye, Mankountan- RN3 (Carrefour Toumbéta) et Hamdallaye-Yaguissiran (RN3) (Lot5)

USD 1,186,210
Guinea

RECRUTEMENT D’UN CONSULTANT (FIRME) POUR LE CONTROLE ET LA SUPERVISION DES TRAVAUX DE REHABILITATION DE 322,638 KM DE PISTES, DE CONSTRUCTION DE QUATRE (4) PONTS AINSI QUE DES INFRASTRUCTURES COMMUNA

USD 1,227,401