Travaux d’aménagement de 64,627 km de routes rurales dans les Régions de Niamey, Tahoua et Zinder pour la deuxième phase du PMRC LOT 1. Région de Niamey : (7,165 Km) - Bretelle site maraicher de
World Bank-financed contract awarded to EGAM for the Niger ENHANCING NIGER NORTHEASTERN CONNECTIVITY project (Project ID P171793).
Overview
Contract awarded under World Bank-financed project P171793 (ENHANCING NIGER NORTHEASTERN CONNECTIVITY). Borrower: Government of Niger. Procurement category: Works. Method: Request for Bids. Review type: Prior. Fiscal year: 2026. Supplier of record (per World Bank STEP): EGAM (Niger). Borrower contract ref: NE-PADEZA-416680-CW-RFB. Source: World Bank Contract Awards in Investment Project Financing dataset, daily updated from STEP.
Selection Criteria
Selected through Request for Bids procurement procedure under World Bank Procurement Regulations. Procurement category: Works. Subject to Prior review by the World Bank.