Back to contract awards
CONTRACT AWARD ★ Featured ✓ Verified Updated yesterday

Extension of Sanankoroba Substation (Mali) - Combined PASEM and PIEGM Contracts, TATA

Combined design, supply and installation contract awarded to TATA for the extension of the Sanankoroba substation in Mali, jointly financed by the Mali Electricity Sector Improvement Project 3 (PASEM) and the Guinea-Mali Interconnection Project (PIEGM).

Key Information
Awarding Country
Awarded By
Energie du Mali (EDM) and Electricite de Guinee (EDG)
Awarded To
TATA
Status
In Progress
Contract Value
USD 8,072,817
Procurement Method
Open
Reference
P166042-PASEM-WORKS-SUBSTATION-SANANKOROBA-TATA
View Original Announcement Opens on the original publisher's site

Description

Two parallel works contracts awarded to TATA for the extension of the Sanankoroba substation in Mali. Contract 1 was signed between the Mali Electricity Sector Improvement Project 3 (PASEM) and TATA for an amount of USD 2,574,037.72 covering design and installation services. Contract 2 was signed between the Guinea-Mali Interconnection Project (PIEGM) and TATA for an amount of USD 5,498,779.50 covering materials and equipment of foreign origin. Since January 2024 the execution of works accelerated and reached an overall progress rate of 69 percent. The main equipment of the substation, including the transformer, was delivered to Mali in early October 2024. Completion of the extension works is scheduled for June 2025. The combined contract value across both PASEM and PIEGM components is USD 8,072,817.22. TATA is the only contractor explicitly named in the publicly disclosed Implementation Status Report for the contracts of the Guinea-Mali Interconnection Project.

Scope of Work

Design and installation services (PASEM contract) and supply of materials and equipment of foreign origin (PIEGM contract) for the extension of the Sanankoroba 225 kV substation in Mali, including the main transformer and related high-voltage equipment.

Why This Supplier Won

TATA was awarded the combined contract package across two financing instruments. PASEM contract for design and installation services valued at USD 2,574,037.72. PIEGM contract for materials and equipment of foreign origin valued at USD 5,498,779.50. Combined total USD 8,072,817.22. Project is financed by IDA credits and grants under the Guinea-Mali Interconnection Project P166042 and the Mali Electricity Sector Improvement Project PASEM.

Sectors

Energy Power Transmission Substations

Source

World Bank Implementation Status and Results Report (ISR02057), Guinea-Mali Interconnection Project P166042, archived 14 November 2024

Related Contract Awards

Mali

L’acquisition d’un engin de prospection et de dépannage en cas d’échouage des bateaux pour le compte de l’ABFN et l’UGP/PREEFN

USD 1,162,029
Mali

L’Agence d’Exécution des Travaux d’Infrastructures et d’Equipements Ruraux (AGETIER - MALI) MISE EN ŒUVRE SOUS-COMPOSANTE 1.1 : DÉVELOPPEMENT DES INFRASTRUCTURES DE GESTION DES DÉCHETS SOLI

USD 1,162,993
Mali

Acquisition de 200 000 masques KN95 et de 10 000 kits d’EPI pour la protection des personnes exposées dans le cadre de la riposte contre la pandémie COVID-19 au Mali

USD 1,174,043
Mali

Lot 01 : Travaux d’aménagement de 72,83 km de piste rurale à Zantiguila - Dioïla avec les aménagements connexes y afférents

USD 1,192,962